July 22, 2009

Construction Updates: July 22 to 31

Freight elevator shut-down
The freight elevator in B wing of the Health Sciences building will be shut down on Friday, July 24 from 7:00 a.m. to noon to facilitate work going on in the area of the elevator shaft. The main elevators in B wing will be running as normal.

Health Sciences B wing re-roofing
Re-roofing work on B-Wing of the Health Science building is scheduled to starting July 27. Work will begin on the south side of the roof. Occupants of the 6th floor will experience an increase in the noise level as the old roofing material is removed. This will require a fair amount of banging and hammering. The contractor has indicated the noisiest work on the south side should be completed by the middle of August. Once the roofing is complete on the south half of the B wing, work will begin on the north half. No dates have been confirmed yet. Health Sciences building occupants will be informed of the progress.

July 13, 2009

Construction updates & notices

There is some good news to pass along. Work on the 3rd floor B wing lobby and elevator area is complete. The two main elevators will once again be stopping on the 3rd floor.

Notices:
Ventilation to B-Wing of the Health Sciences building will be off on Saturday July 18, 2009 and will remain off until 6:00 a.m. on Monday, July 20, 2009 to facilitate ongoing work related to asbestos removal in the building. In addition, access to the 5th floor east and north hallways of the Health Sciences building will be closed as work takes place in the hallways.

Demolition of the annex located on the north side of the Health Sciences Building is near completion. When finished, crews will move in to start digging for construction of the lower level of the north side of D wing.